Friday 28 February 2014

Bricks Day 5 Washout

I'm calling it early.  Absolutely hammering down rain outside. Today is a write off. Bricks should dry out by Monday :)

UPDATE:

Took Kel to the station and walked up to have a look.. Lots of water around. Hopefully when the build is complete and the surface water drainage pipes are completed(and the rest of the landscaping..), this will be less of an issue

Weatherzone says we took over 200mm of rain overnight.

Lots of water

Lots of water

At least the drain is doing it's job for the most part

Water down the side

Bit blurry this one

Water up the side

Water around the rear of the house

Bit of sand got washed away


Thursday 27 February 2014

Bricks Day 4

Another day with very little action. A lot of rain around at the moment. It is raining outside now, so we are hoping it dries up for tomorrow

One alfresco wall completed

Protruding walls for built in robes and furniture recesses.

Protruding walls for built in robes and furniture recesses

Wednesday 26 February 2014

Bricks Day 3

So, there was a bit of rain today. A bit of brick work was completed however.

Garage wall.. Lots of crap bricks in the foreground:)

looking up the right hand side

Closeup.. cant wait for the cleaning.

Alfresco wall

Rear right

rear right

Tuesday 25 February 2014

Bricks day 2

Just a little more progress..

Front room

Looking at the patio area

Left side of Garage

Side of the garage

Monday 24 February 2014

Bricks Day 1

Bricklayers have attended this morning and started work. Not a lot was completed on the first day, but i did not expect that. Hopefully tomorrow we will have a wall or two!

Start of brickwork

Monday 17 February 2014

Frames complete, windows in

Received notification that the frames had been completed today. We went to have a look after work, and the windows and stacker doors have also been installed!

Front windows

View from the side

Main bedroom and great room stacker doors

On the weather front it is still sprinkling intermittently and forecast for more.. With bricks and sand on its way, still hoping for the best! :)

Saturday 15 February 2014

Frames day 3

There was not a lot of noticeable change today. They finished off 'almost' all of the framing but there is a few small bits left. The main bit that I noticed completed, was the roof area over the patio. It kind of makes the facade take on a bit more shape.

Patio area completed
OK, so we were excited to get the dunny as it meant that the build was starting, but now, not so sure. It is in every picture of the front! Wish they would move it :)

The conduit for the electricity has also been buried.

I received a call from the site supervisor yesterday. This was our first contact with him. He introduced himself and gave me an update. I don't think he realizes I am only 5 minutes down the road and obsessively drive past the block numerous times per day. Anyway, he said the frames should be completed by Monday and he hopes to have the bricks and brickies on site by the end of the week. If not, the Monday after the weekend(24th Feb?).

On the weather front, it is drizzling outside now. Certainly not building weather. So Mother nature, lets get this rain out of the way before the working week recommences :)

Thursday 13 February 2014

Frames day 2

Well, not a lot to say today other than Wow! It is looking more and more like a house every day. With we weather forecast for the next few days, I am just hoping they can fit in the last ew sections of the roof trusses tomorrow. Hope the rain holds off!

Just a few pics










Wednesday 12 February 2014

Frames day 1

So, we expected the frames to be delivered today.. little did we know they were also going to commence putting them up! Was a nice surprise to come home to!

View from rear

View from rear

Right Side view

Front right corner

Front view

It is now starting to feel like we are actually building a house!

Tuesday 11 February 2014

Termite barrier

Not a great deal happened on the block yesterday. They did come and install the termite barrier though. Did not really expect anything to be done, as the next big thing is the frames, which I have been told should be delivered tomorrow (Wednesday). Sunny weather outside today after a somewhat gloomy start. Just the kind of day you would want to be building a house! :)

Termite Barrier around the perimeter

Saturday 8 February 2014

Slabbed!

Well, I am a day late with this post. Yesterday the slab was poured and formwork removed(from most of it)

After all this time waiting, we finally have some form of structure on the block that forms part of a house! :)

View from Station Street(Main road)

Concrete pump pouring the slab

Pouring the slab


Finished slab

Front patio still with formwork.

Looking over the fence

Drop edge in to the garage

Slab from the rear of the house

Slab from rear of the house