Important Dates

Holding Deposit on Land 17th February 2013
$3000 Deposit on Santorini 23rd February 2013
5% Deposit on Land 12th March 2013
Pre-Selections Walkthrough 19th March 2013
Colour Selections 15th May 2013
Colours signed 16th May 2013
Contract plans signed 31st July 2013
Land Registered 28th October 2013
Advised of Land registration 31st October 2013
Plans lodged with council 7th November 2013
Electrical appointment 25th November 2013
Settlement on land 27th November 2013
DA Approved 27th November 2013
CC Approved 27th November 2013
Tree removed 8th December 2013
Construction list! 12th December 2013
Site pegged 17th January 2014
Site cut 22nd January 2014
Portaloo and sediment control 23rd January 2014
Security Fence 24th January 2014
Plumbing/Pipework 30th January 2014
Piering and formwork started 5th February 2014
Slab completed 7th February 2014
Framing commenced 12th February 2014
Framing Complete 17th February 2014
Brickwork commenced 24th February 2014
Gutters and Fascia 12th March 2014
Brickwork completed 15th March 2014
Roofing completed 17th March 2014
Pre Gyprock site inspection 18th March 2014
Eaves completed 20th March 2014
Gyprock started 24th March 2014
Waterproofing and Garage Door 4th April 2014
Pre Tiling inspection 15th April 2014
Floor Tiling commenced 16th April 2014
Driveway Poured 17th April 2014
Wet area floor tiling completed 28th April 2014
Painting commenced 28th April 2014
Painting completed 6th May 2014
Internal plumbing 6th May 2014
Electrical fitoff 8th May 2014
PCI 27th May 2014
Handover 17th June 2014
Commence retaining walls 6th August 2014
Front Turf 15th November 2014
Rear excavation 25th November 2014
Front retaining walls completed 14th December 2014
Commence rear retaining walls 3rd March 2015
Rear Retaining walls complete 4th July 2015
Rear turf prep commenced 8th August 2015
Clothesline 11th August 2015
Full Occupancy Certificate! 18th August 2015
Rear turf prep complete 19th August 2015
Rear Turf installed 21st August 2015
Side fence installed 30th September 2015
Rear fence installed 2nd October 2015
Aaron's Birthday 13th June 1994
Emily's Birthday 12th August 2001
Bella's Birthday 5th December 2002

No comments: