| Holding Deposit on Land | 17th February 2013 |
| $3000 Deposit on Santorini | 23rd February 2013 |
| 5% Deposit on Land | 12th March 2013 |
| Pre-Selections Walkthrough | 19th March 2013 |
| Colour Selections | 15th May 2013 |
| Colours signed | 16th May 2013 |
| Contract plans signed | 31st July 2013 |
| Land Registered | 28th October 2013 |
| Advised of Land registration | 31st October 2013 |
| Plans lodged with council | 7th November 2013 |
| Electrical appointment | 25th November 2013 |
| Settlement on land | 27th November 2013 |
| DA Approved | 27th November 2013 |
| CC Approved | 27th November 2013 |
| Tree removed | 8th December 2013 |
| Construction list! | 12th December 2013 |
| Site pegged | 17th January 2014 |
| Site cut | 22nd January 2014 |
| Portaloo and sediment control | 23rd January 2014 |
| Security Fence | 24th January 2014 |
| Plumbing/Pipework | 30th January 2014 |
| Piering and formwork started | 5th February 2014 |
| Slab completed | 7th February 2014 |
| Framing commenced | 12th February 2014 |
| Framing Complete | 17th February 2014 |
| Brickwork commenced | 24th February 2014 |
| Gutters and Fascia | 12th March 2014 |
| Brickwork completed | 15th March 2014 |
| Roofing completed | 17th March 2014 |
| Pre Gyprock site inspection | 18th March 2014 |
| Eaves completed | 20th March 2014 |
| Gyprock started | 24th March 2014 |
| Waterproofing and Garage Door | 4th April 2014 |
| Pre Tiling inspection | 15th April 2014 |
| Floor Tiling commenced | 16th April 2014 |
| Driveway Poured | 17th April 2014 |
| Wet area floor tiling completed | 28th April 2014 |
| Painting commenced | 28th April 2014 |
| Painting completed | 6th May 2014 |
| Internal plumbing | 6th May 2014 |
| Electrical fitoff | 8th May 2014 |
| PCI | 27th May 2014 |
| Handover | 17th June 2014 |
| Commence retaining walls | 6th August 2014 |
| Front Turf | 15th November 2014 |
| Rear excavation | 25th November 2014 |
| Front retaining walls completed | 14th December 2014 |
| Commence rear retaining walls | 3rd March 2015 |
| Rear Retaining walls complete | 4th July 2015 |
| Rear turf prep commenced | 8th August 2015 |
| Clothesline | 11th August 2015 |
| Full Occupancy Certificate! | 18th August 2015 |
| Rear turf prep complete | 19th August 2015 |
| Rear Turf installed | 21st August 2015 |
| Side fence installed | 30th September 2015 |
| Rear fence installed | 2nd October 2015 |
| Aaron's Birthday | 13th June 1994 |
| Emily's Birthday | 12th August 2001 |
| Bella's Birthday | 5th December 2002 |
Important Dates
Subscribe to:
Comments (Atom)
No comments:
Post a Comment