Our landscaper completed the landing and the final three steps to the patio yesterday. He is coming back this morning to finish the concrete on the landing and then the final step will be the pavers for the step treads and landing which will occur next week sometime when the concrete has set!
Saturday, 18 October 2014
Friday, 17 October 2014
More retaining wall :)
Saturday, 11 October 2014
Block cores and backfill
Concrete truck arrived just before 8am. Straight in to it.
The backfill ended up a little too wide which meant we ran out of backfill a little early, but we managed to scoop some back up.
Was too busy to get any photos in progress, but this is the end result
Dean and Chris giving a hand |
Cores filled |
Done. Scraped some back up to increase the height |
Big shout out to My FIL who came to give a hand, and neighbours Chris and Dean who seen the work happening and came over to lend a hand. Cheers guys! Beers are on me tonight!
Now, the side walls are going to be a PITA as we cannot get a truck anywhere near to close. Will all have to be carted in by barrow.
Tuesday, 7 October 2014
Retaining walls awaiting core and backfill
Well that's it. Blocks are laid and awaiting core filling and backfill with no fines concrete.
Engineer is booked for Friday inspection and concrete will arrive 8am Saturday!
Engineer is booked for Friday inspection and concrete will arrive 8am Saturday!
Wednesday, 1 October 2014
More retaining wall progress
The Footings/path down the dead side of the house was poured today. Really happy with the finish. Our landscaper is putting in the base course, and we are doing the rest.
And here is the base course at the front.
After he left, I thought I may as well put in an hours work, and here is the results!
Just poured |
Finished and base course down |
And here is the base course at the front.
Steps to be built to the left of the wall up to the Patio |
After he left, I thought I may as well put in an hours work, and here is the results!