Holding Deposit on Land | 17th February 2013 |
$3000 Deposit on Santorini | 23rd February 2013 |
5% Deposit on Land | 12th March 2013 |
Pre-Selections Walkthrough | 19th March 2013 |
Colour Selections | 15th May 2013 |
Colours signed | 16th May 2013 |
Contract plans signed | 31st July 2013 |
Land Registered | 28th October 2013 |
Advised of Land registration | 31st October 2013 |
Plans lodged with council | 7th November 2013 |
Electrical appointment | 25th November 2013 |
Settlement on land | 27th November 2013 |
DA Approved | 27th November 2013 |
CC Approved | 27th November 2013 |
Tree removed | 8th December 2013 |
Construction list! | 12th December 2013 |
Site pegged | 17th January 2014 |
Site cut | 22nd January 2014 |
Portaloo and sediment control | 23rd January 2014 |
Security Fence | 24th January 2014 |
Plumbing/Pipework | 30th January 2014 |
Piering and formwork started | 5th February 2014 |
Slab completed | 7th February 2014 |
Framing commenced | 12th February 2014 |
Framing Complete | 17th February 2014 |
Brickwork commenced | 24th February 2014 |
Gutters and Fascia | 12th March 2014 |
Brickwork completed | 15th March 2014 |
Roofing completed | 17th March 2014 |
Pre Gyprock site inspection | 18th March 2014 |
Eaves completed | 20th March 2014 |
Gyprock started | 24th March 2014 |
Waterproofing and Garage Door | 4th April 2014 |
Pre Tiling inspection | 15th April 2014 |
Floor Tiling commenced | 16th April 2014 |
Driveway Poured | 17th April 2014 |
Wet area floor tiling completed | 28th April 2014 |
Painting commenced | 28th April 2014 |
Painting completed | 6th May 2014 |
Internal plumbing | 6th May 2014 |
Electrical fitoff | 8th May 2014 |
PCI | 27th May 2014 |
Handover | 17th June 2014 |
Commence retaining walls | 6th August 2014 |
Front Turf | 15th November 2014 |
Rear excavation | 25th November 2014 |
Front retaining walls completed | 14th December 2014 |
Commence rear retaining walls | 3rd March 2015 |
Rear Retaining walls complete | 4th July 2015 |
Rear turf prep commenced | 8th August 2015 |
Clothesline | 11th August 2015 |
Full Occupancy Certificate! | 18th August 2015 |
Rear turf prep complete | 19th August 2015 |
Rear Turf installed | 21st August 2015 |
Side fence installed | 30th September 2015 |
Rear fence installed | 2nd October 2015 |